In the early morning of November 22 he produced a damage in the main Transformer of Gas Turbine, of the Steam Power Plant of GICC of ELCOGAS, whose causes are being investigated. As a consequence of the same one, the production of the plant he has gotten interrupted.
The electric power once 15.75 kilovolts was produced in the generator rises in the Transformer to 220 kilovolts and happens to the transporting line, therefore, although the plant is in perfect running conditions, when not counting on this team he finds itself stationary.
Behind the evaluation of the damage and in front of the probability that your reparation takes more time in time, the possibility of substituting the transformer for another one, is studied of provisional way.