During the commissioning, many activities were carried out in order to prepare the plant for correct operation. Besides ELCOGAS, other companies like Air Liquide Paris, Black & Veatch, Electricidade de Portugal (EDP), Krupp Uhde/Babcock Wilcox Española, Siemens/Babcock Wilcox Española, and Siemens Disel Sainco were involved in this phase.
Experience in this field is summarized as follows:
- Management of interfaces between the collaborating engineering companies and equipment/technology suppliers: minimization of the impact caused by overlap between the Preparation, Construction and Commissioning activities.
- Construction by stages requiring two marketing operations.
- Methods to compensate for lack of experience in the design, construction and implementation of gasification processes.
- Adapting the progress plan from a design company to an operating power plant as part of the Project Execution.
- Demonstration of equipment scale-up in different systems: fuel preparation and feeding system, gasifier, quench gas compressor, etc.
- Procedures for efficient and economic management of interfaces (air, oxygen, coal gas, nitrogen, etc.), especially during commissioning.
Key dates
Start |
End | |
---|---|---|
BOP I (Balance of Plant) | June 95 | January 96 |
Combined cycle | January 96 | September 96 |
BOP II | September 96 | February 97 |
Air Separation Unit | September 96 | June 97 |
Gasification (including Coal Preparation) | January 97 | March 98 |