SITE CONDITIONING
Start of works
4/93
Surveying
7/93
Drawings, measurements and levels
7/93
Drainage
9/93
Earthworks
11/93
Substation installation
12/93
Road fixing
12/93
CIVIL ENGINEERING
 
Steam turbine building
2/94
Gasification piles
6/94
HRSG Structure
8/94
Combined cycle works
10/94
Concrete gasification tower
10/94
Combined cycle works
10/94
Cooling tower
1/95
Gasification structure installation
3/95
MANUFACTURING AND TRANSPORTATION
Gas turbine external casing
12/93
Steam turbine (HP) casing
12/93
Recovery boiler pipes
7/94
Gas turbine transportation
1/95
Gas turbine arrival
1/95
Transport of the HRSG modules
1/95
Gasifier parts
1/95