SITE CONDITIONING
Start of works 4/93 |
Surveying 7/93 |
Drawings, measurements and levels 7/93 |
Drainage 9/93 |
Earthworks 11/93 |
Substation installation 12/93 |
Road fixing 12/93 |
CIVIL ENGINEERING
Steam turbine building 2/94 |
Gasification piles 6/94 |
HRSG Structure 8/94 |
Combined cycle works 10/94 |
Concrete gasification tower 10/94 |
Combined cycle works 10/94 |
Cooling tower 1/95 |
Gasification structure installation 3/95 |
MANUFACTURING AND TRANSPORTATION
Gas turbine external casing 12/93 |
Steam turbine (HP) casing 12/93 |
Recovery boiler pipes 7/94 |
Gas turbine transportation 1/95 |
Gas turbine arrival 1/95 |
Transport of the HRSG modules 1/95 |
Gasifier parts 1/95 |